TEZU AIRPORT

Name of Work Construction of Terminal Building and Allied Works (Balance Works) at Tezu Airport.
Client Airport Authority of India (AAI)
Cost of Project Rs 84.15 Cr.
Date of Completion 30.04.2023
Scope of Work Design, drawing, Award of work, implementation of modern Airport buildings incl. Civil & Structural finishes of work, aluminium roofing, cladding work, flooring, Structural Glazing with all Electrical, Plumbing, Air conditioner, HVAC, Fire Fighting, Security system, Glass partition, Lift Work, including control tower in steel structure (PEB) & Allied finishing works, connecting roads, parking, Horticulture Work, sewerage system, STP, tube-well & pump room.
Airport Project Image
2 / 3
SHILLONG AIRPORT

Name of Work Construction of New ATC Tower Cum Fire Station (Balance Works) at Barapani Airport Shillong.
Client Airport Authority of India (AAI)
Cost of Project Rs 14.54 Cr.
Date of Completion 11.11.2024
Scope of Work
  1. Design, drawing, Award of work, implementation of modern Airport buildings incl. Civil & Structural including control tower in steel structure (PEB) & Allied finishing works, Emergency road connecting to runway.
  2. External Development work including sewerage system, horticulture and tube well and Finishing work including roofing, External cladding work, flooring, Structural Glazing and Sanitary installations and plumbing etc.
  3. Supply Installation, Testing and Commissioning of Internal and External Electrical works including SITC of Panel and SITC of complete building Fire Fighting system including Under Ground Pump room and Fire Tank.
  4. SITC of Air Conditioner HVAC System, SITC of Fire Control System, Data Networking & Telephone EPBAX exchange works, Security system including SITC of CCTV System and Access Control System, Plumbing, Air Conditioner, HVAC, Fire Fighting, Security system
Airport Project Image
3 / 3
JOHART AIRPORT

Name of Work Construction of New ATC Tower Cum Fire Station (Balance Works) at Barapani Airport Shillong
Client Airport Authority of India (AAI)
Cost of Project Rs 14.54 Cr.
Date of Completion 11.11.2024
Scope of Work Construction of CISF Barrack, Kote& Dog Kennel at Lichubari and other associated work at Jorhat Airport, Assam